Est. reading: 9 minutes

Sunrise Energy Metals Scandium: The Deep Dive

Sunrise Energy Metals has approved a scandium mine in New South Wales. It’s designed to make 60 tonnes of scandium oxide a year. That’s about what the US Geological Survey estimates the whole world used in 2025. Scandium is a little-known metal that strengthens aluminium and runs some fuel cells, and China, the leading producer, […]

Sunrise Energy Metals has approved a scandium mine in New South Wales. It’s designed to make 60 tonnes of scandium oxide a year. That’s about what the US Geological Survey estimates the whole world used in 2025.

Scandium is a little-known metal that strengthens aluminium and runs some fuel cells, and China, the leading producer, has required a government licence to export it since April 2025.

Here is what changed, why the metal is hard to get, who carries the risk, and what to watch next.

What changed

On 2 November 2026, Sunrise Energy Metals (ASX: SRL) announced that its board had approved the final investment decision to build the Syerston scandium project, near Fifield in central west NSW. The company, chaired by mining financier Robert Friedland, calls it the world’s first primary scandium mine.

The plan is to process 64,000 tonnes of ore a year into 60 tonnes of scandium oxide that is more than 99.9% pure, with first production targeted for the second half of 2028. The mine and refinery are estimated to cost about US$322 million (about A$456 million, as reported by the Australian Financial Review), over a 24 month build. The plan runs for 32 years: 21 years of open pit mining, then 11 years of processing stockpiled ore.

Behind the decision sits a conditional commitment, announced in August, of up to US$400 million in long term loans from the US Department of War’s Office of Strategic Capital, over a proposed 25 year term. Sunrise also had A$148.1 million of cash at 30 September. The NSW Government has accepted the project into its critical minerals royalty deferral scheme, which delays royalties for five years, though they must still be paid in full.

On the day of the announcement, SRL shares closed up 1.19% at A$11.94, according to exchange data. That was about half their closing price of A$23.13 on 24 September, although well above their 52 week low of A$4.11. Past performance is not a reliable indicator of future performance.

Why scandium is hard to get

Scandium is a very small market. The US Geological Survey estimates the world used about 60 tons of scandium oxide in 2025 and produced about 80 tonnes, from capacity of over 90 tonnes.

Its main uses were aerospace alloys, where a small amount makes aluminium stronger, and solid oxide fuel cells, which generate power on site. Sunrise says such fuel cells are being used to power AI data centres.

No one mines scandium as a main product today, though Ukraine did until 2003 and the United States until 1969.

The USGS says current supply is produced only as a byproduct, recovered from the waste of nickel, titanium and alumina processing, and that China was the leading producer.

How large China’s share is depends on the source: Sunrise puts it at over 85% of refined supply, while the Modern War Institute at West Point puts it at over 90%.

Either way, most refined scandium comes from China. The United States mined none in 2025 and imports all it uses.

China’s control

On 4 April 2025, China’s Ministry of Commerce put scandium metal, alloys, oxide and compounds under export control, so exports need a government licence. That is a licence system, not a ban.

In November 2025 the White House said China would issue general licences for US end users, which it described as the de facto removal of the controls.

But the USGS reported that by December 2025 the April controls remained in effect, although China had begun issuing general licences to selected exporters.

Supply has not settled since then. In May 2026, the White House said China would address US concerns about shortages of critical minerals, naming scandium. In September it said the two countries were still working to get shipments back to appropriate levels.

Sunrise goes further, saying scandium supply to key Western markets has all but ceased. No government source measures scandium shipments, so that remains the company’s description.

Pieces inside and outside China

Prices inside and outside China have also moved apart.

The USGS lists Chinese scandium oxide at about US$640 a kilogram in 2025, down from about US$890 to US$1,000 in 2021, a slide that began before the 2025 rules.

Outside China it costs far more: the US stockpile planned to buy more than 6,000 kilograms from Quebec for as much as US$40 million, which works out to up to about ten times the Chinese price, though that is a ceiling (the minimum order is US$2 million) and for slightly lower-purity oxide.

Who carries the risk

SRL shareholders carry the project risk. Sunrise has no revenue from scandium yet, and its value rests on three things: building the mine on budget, drawing the US loan, and signing buyers.

The loan is not yet binding. Sunrise’s quarterly report says the terms are non binding, and the August announcement says each drawdown depends on project milestones, equity put in by the company and binding offtake agreements, meaning signed contracts to sell its output.

None has been signed.

Lockheed Martin holds an option to buy the first 15 tonnes a year for five years, about a quarter of planned output, but that is subject to formal offtake terms. Sunrise says talks with other buyers continue.

The US money also comes with a corporate change. A condition of the loan is that Sunrise moves its parent company to the United States and lists on Nasdaq. Under the plan, holders receive one ASX traded CHESS Depositary Interest for each SRL share, or could choose Nasdaq listed shares instead. The scheme needs approval from shareholders, the Federal Court and foreign investment regulators.

The market size cuts both ways. Syerston’s planned 60 tonnes a year matches the world’s 2025 consumption, so a new mine could ease the shortage for Western buyers. It could also struggle to sell its full output at prices above China’s.

The Minor Metals Trade Association estimates that Bloom Energy, the US fuel cell maker reckoned to be the largest buyer, may need about 200 tonnes a year by the early 2030s, but it also expects Sunrise to be unlikely to deliver in volume before 2029.

For the ASX, SRL is the direct listed link. Rio Tinto runs the only scandium oxide plant in North America, in Quebec, but scandium is a very small part of its business.

What to watch

The first date is Tuesday 10 November 2026. China’s own notice suspends its wider October 2025 rare earth package, including licences on re-exports from other countries, only until that day.

US officials, and China’s commerce ministry in a 28 September statement, say the broader arrangement runs to 10 January 2027, but no numbered Chinese notice amending the suspension has been published.

The April 2025 licence rule on scandium was never part of the suspension and stays either way. A published Chinese notice extending the pause may keep the wider package on hold; with no notice by 10 November, the legal text points to its return.

For Sunrise, the instruments are company announcements. Its annual general meeting is on Thursday 12 November 2026, and its scheme meeting and Nasdaq listing are indicated for December 2026.

The two documents that can turn plans into commitments are signed loan documents with the Office of Strategic Capital and a first binding offtake contract.

An announcement of either may remove one of the conditions on the US money; a slip past the scheme’s end date of 31 March 2027 could show the timetable under strain.

Trump and Xi are also expected at APEC in Shenzhen on 18 and 19 November.

Frequently asked questions

What is the Sunrise Energy Metals scandium project?

Syerston, near Fifield in central west NSW, is a planned scandium mine and refinery. Sunrise approved it on 2 November 2026 at an estimated cost of about US$322 million, targeting 60 tonnes a year of high purity scandium oxide from the second half of 2028.

Has China banned scandium exports?

No. Since 4 April 2025, China has required a government licence to export scandium metal, alloys, oxide and compounds, and that rule has never been lifted. Since late 2025 some Chinese exporters have held general licences that cover repeated exports for up to three years. The White House said in 2025 that general licences would amount to de facto removal for US users, but in 2026 it still reported shortages naming scandium.

What is scandium used for?

Mostly in aerospace aluminium alloys and solid oxide fuel cells, according to the USGS, with smaller uses in electronics and military equipment. Sunrise says the fuel cells are being used to power AI data centres.

Sources

Superhero does not provide financial advice that considers your personal objectives, financial situation or particular needs. All investments carry risk so please consider carefully before investing and be aware that past performance is not indicative of future performance. Graphics, charts and graphs provided for illustrative purposes only. View our FSGs to consider if Superhero is appropriate for you. Superhero Markets Pty Ltd (ABN 36 633 254 261) is a Corporate Authorised Representative (CAR 1276309) of Superhero Securities Limited (ABN 96 160 456 315, AFSL 430150).

Read our latest articles

Start building your momentum today.

This information is general in nature and does not take into account your personal financial situation, objectives, or needs. You should consider whether any product is appropriate for you and seek independent financial advice if needed. Investments can go up as well as down. Past performance is not a reliable indicator of future performance. For superannuation products, please read the relevant Product Disclosure Statement (PDS) before making a decision. Digital assets are highly volatile and carry significant risk. Other fees and charges may apply.